Salesforce Certified Agentforce Field Service and Operations Consultant free question 6 / 10 · Domain 3: Managing Scheduling and Optimization
A scheduling policy gives the Minimize Travel objective a weight of 100. An option adds one hour of travel. According to the Help, how is the contribution of this objective to the schedule score derived?
- One hour is 100% of the scale, and that grade is multiplied by the weight
- One hour is 50% of the 0 to 2 hour scale, and that grade is multiplied by the weight
- The weight is divided by the hours of travel, and the result is the score
- The objective gives a constant score per appointment, independent of the travel time
Show the answer and explanation
Answer: B
Why this is correct
The page on service objectives explains that each objective has a scale that defines the best and worst cases. For Minimize Travel the best case is no travel and the worst case is 2 or more hours of travel, and the travel time is graded across this scale so that 1 hour of travel is 50% of the scale. The derived grade is multiplied by the weighting defined in the scheduling policy to determine the score for that objective, and the sum over the objectives gives the score of the schedule.
Why the other options are wrong
"One hour is 100% of the scale, and that grade is multiplied by the weight" … The worst case is 2 or more hours of travel. Travel time is graded across the scale, so one hour is half of it.
"The weight is divided by the hours of travel, and the result is the score" … The grade from the scale is multiplied by the weight. The weight is not divided by hours.
"The objective gives a constant score per appointment, independent of the travel time" … Travel time is graded across the scale. The score changes with the amount of added travel.
Key points
Score is grade times weight, summed over the objectives. The same grade counts for more when its objective has a higher weight.