Salesforce Certified Business Analyst free question 10 / 10 · Domain 6: Development Support and User Acceptance
A manager proposes giving UAT to a separate tester who has no history on the project. Why does the expert say the BA role matters in UAT?
- The BA is independent of the project, which means the results are judged free of bias from earlier decisions
- The BA understands the system’s functionality and intention, and brings project context from requirements
- The BA is trained to automate the test cases, so that UAT can be repeated for later releases and projects
- The BA has the authority to approve production releases on behalf of the technology team and the business
Show the answer and explanation
Answer: B
Why this is correct
In the Transcript, the director says the BA role is imperative for UAT because BAs understand the functionality and the intention of the system that is being developed. The BA played a critical role earlier, during the business requirements, and so brings the project context to UAT. BAs are also detail oriented by nature and can help uncover potential problems. A tester who was not there for the earlier meetings may not see the whole story.
Why the other options are wrong
"The BA has the authority to approve production releases on behalf of the technology team and the business" … The expert’s reason is the BA’s understanding of the system and its intent. Release approval comes from the written sign-off of the business stakeholders.
"The BA is trained to automate the test cases, so that UAT can be repeated for later releases and projects" … The expert points to the BA’s understanding of the functionality and the project context, not to test automation.
"The BA is independent of the project, which means the results are judged free of bias from earlier decisions" … The expert argues the opposite: the BA was present for the requirements and brings project context, which a separate tester would lack.
Key points
In the ideal case, the director says, the BA is there at the start of the project and handles the requirements and the engagement with the project team.