Salesforce Certified Platform Development Lifecycle and Deployment Architect Practice Questions

Salesforce Certified Platform Development Lifecycle and Deployment Architect exam preparation

Salesforce Certified Platform Development Lifecycle and Deployment Architect practice questions in English: 180 questions with explanations. The mock exam has 60 questions and 105 minutes.

Salesforce Certified Platform Development Lifecycle and Deployment Architect free question 6 / 10 · Domain 5: Deploying

Three Metadata API deployments are started against the same org within a few minutes. What does the Metadata API Developer Guide say happens to them?

  1. One deployment runs at a time, and the others wait under Pending Deployments in the order they will be executed
  2. The other two are merged into the running deployment, the page tracking them with one chart of components
  3. The other two are rejected until the first of the deployments completes, and the team has to start them again
  4. The three run at once, and the Deployment Status page shows a separate progress chart per deployment
Show the answer and explanation

Answer: A

Why this is correct
The guide explains that you can initiate multiple deployments, but only one deployment can run at a time. The other deployments remain in the queue waiting to be executed after the current deployment finishes. Queued deployments are listed under Pending Deployments in the order they will be executed, and you can check or cancel deployments that are in progress or in the queue from the Deployment Status page.

Why the other options are wrong
"The three run at once, and the Deployment Status page shows a separate progress chart per deployment" … The guide says only one deployment can run at a time. The Deployment Status page shows real-time progress for the current deployment.
"The other two are merged into the running deployment, the page tracking them with one chart of components" … The guide says the other deployments remain in the queue waiting to be executed after the current deployment finishes. It doesn't describe merging them.
"The other two are rejected until the first of the deployments completes, and the team has to start them again" … The guide says you can initiate multiple deployments. The others remain in the queue and are listed under Pending Deployments.

Key points
Queued deployments aren't lost and aren't parallel. They run one after the other.