ServiceNow CIS-SPM free question 1 / 10 · Domain 2: SPM Financials

You create a new cost plan in Project Workspace and select Labor Capex as the Cost type. According to the official description of the Create cost plan form, what happens to the Employee type field of this cost plan?

  1. External is filled in, and the field is read-only so it cannot be changed
  2. External is filled in, and the user can change it to Internal
  3. Internal is filled in, and the field is read-only so it cannot be changed
  4. Internal is filled in, and the user can choose a different type
Show the answer and explanation

Answer: C

Why this is correct
On the Create cost plan form in Project Workspace, Employee type is a read-only field. It is External when Cost type is External labor Capex or External labor Opex, and Internal when Cost type is Labor Capex or Labor Opex. Because you selected Labor Capex, Internal is filled in and the user cannot change it. Choosing the cost type is what decides whether the work is internal or external.

Why the other options are wrong
"External is filled in, and the user can change it to Internal" … Labor Capex corresponds to Internal. Employee type is read-only, and it is not a field you pick again.
"External is filled in, and the field is read-only so it cannot be changed" … The read-only part is right, but External is filled in only when you select External labor Capex or External labor Opex.
"Internal is filled in, and the user can choose a different type" … The value is right, but the documentation describes Employee type as a read-only field.

Key point
On the same form, the Role and Product model fields appear according to the selected Cost type. Product model can be selected when Cost type is Software, Hardware, or Other, for Capex or Opex. On the expense line form, Cost type is filled in with the cost plan value by default.